Home › Installer guides › G99 application guide
Installer guide
For solar and battery installers. When you need G99, what to send, and the mistakes that stall installs for weeks.
By Kevin Mallon, founder · Checked 24 November 2026
Short answer: if the total generation at the property goes over 16 A per phase (3.68 kW single phase, 11.04 kW three phase), or the kit isn't fully type tested, you apply to the network operator under G99 before you fit, and you wait for their answer before you switch on. Small systems often go through a fast track. Bigger ones get a connection offer, sometimes with costs.
| Route | When it applies |
|---|---|
| G98 | Up to 16 A per phase in total at the property (3.68 kW single phase, 11.04 kW three phase), fully type tested. Fit, then notify within 28 days. |
| G99 fast track | Small type-tested systems just over the G98 limit. Apply first; the answer is much quicker than a standard application. |
| G99 standard | Everything else. Apply and wait for the network operator's connection offer before you switch on. |
Existing solar and batteries count towards the limit. A battery added to an existing 3.68 kW system usually means G99. Check a job with our G98 or G99 checker →
| Problem | What happens |
|---|---|
| Missing information | One wrong or missing detail and the application goes back to you. The clock stops until you answer. |
| Existing kit forgotten | Old solar or a battery nobody mentioned changes the total, and the application is wrong from the start. |
| Phase and fuse not confirmed | "Not sure" on the survey becomes a question from the network operator weeks later. |
| Works required | On some networks the operator needs to do work before you can connect, and may quote for it. Better to know before the customer signs. |
| Nobody chasing | Applications sit. If no one owns the follow-up, the install date slips. |
| No proof on file | Your assessor will ask for the application and the answer. An inbox full of threads doesn't count. |
Every GB network operator, plus Northern Ireland, takes low carbon applications through the Energy Networks Association's free Connect Direct platform, as well as their own forms. Some applications are approved straight away when every check passes; the rest go to a connection engineer.
How we take it off you
Don't chase a network operator again.We prepare your G99 from the job, submit it, chase it and file every reply, from £150 up to 50 kW. You get told when the answer lands. We never promise approval: that's the network operator's call.
G99 application serviceRelated
When total generation at the property goes over 16 A per phase (3.68 kW single phase or 11.04 kW three phase), including existing solar and batteries, or when the equipment isn't fully type tested.
You can't switch on until the network operator has given its answer. Many installers wait for approval before booking the install, so the job doesn't stall.
Often. A battery added to an existing 3.68 kW single-phase system usually takes the total over the G98 limit.
Network operators handle applications through their own processes, and some larger connections need works the operator charges for. With us, preparing, submitting and chasing it is from £150 up to 50 kW.
Yes. The Energy Networks Association's Connect Direct platform is free for installers.