Installer guide
Applying to SSEN for a solar or battery job: which route, which form, and what to check first.
By Kevin Mallon, founder · Checked 24 November 2026
Short answer: Scottish and Southern Electricity Networks (SSEN) runs a G99 fast track by email, aiming to respond within 10 working days. You can't connect until it confirms, then you have up to 3 months to install and commission, with form A3-2 due within 28 days of completion.
The north of Scotland and central southern England. Not sure? Check the property's postcode on the network operator's own site before you apply.
| Job | How it goes to SSEN |
|---|---|
| G99 fast track | Forms A3-3 (SGI-1) or A1-2 (SGI-2 and SGI-3), plus SSEN's loop impedance form. SSEN aims to respond within 10 working days. |
| After approval | Up to 3 months to install and commission, then form A3-2 within 28 days of completion. |
| Larger or not type tested | A full G99 application. |
Every GB network operator also takes low carbon applications through the Energy Networks Association's free Connect Direct platform.
How we take it off you
Send us the job. We'll deal with SSEN.We prepare your G99 from the job, submit it, chase it and file every reply, from £150 up to 50 kW. G98 is included on every job with the paperwork service. We never promise approval: that's the network operator's call.
G99 application serviceRelated
Use SSEN's own G99 forms or the Energy Networks Association's Connect Direct platform. Small type-tested systems may qualify for the fast track.
Within 28 days of commissioning.
Don't switch on until the network operator has given its answer. Book the install once you have it.
Yes. G99 applications from £150 up to 50 kW, and G98 is included with the paperwork service.