G98 notifications and G99 applications

G98 and G99, done and filed. Without chasing a DNO at 9pm.

You know the rules. What catches installers out is the paperwork around them: a G98 that slips past 28 days, a battery that quietly tips a job into G99, and a DNO reference nobody filed when the assessor asks.

Where it goes wrong

The 28 days slipG98 is fit and inform: notify the DNO within 28 days of commissioning. On a busy month that's the first thing to drift.
The battery you didn't countThe 16 A per phase limit is for everything at the premises, existing kit included. A battery added to an existing 3.68 kW system usually means G99.
Three-phase assumptionsThree-phase gives you 11.04 kW under G98, but only if the survey confirmed it. "Not sure" on the survey is where mistakes start.
No proof on fileYour assessor wants to see the notification and the DNO's reference. Emails buried in an inbox don't count.

The numbers that matter

RouteLimit (total at the premises)What you do
G98Up to 16 A per phase: 3.68 kW single phase, 11.04 kW three phase (fully type tested)Fit, then notify the DNO within 28 days of commissioning
G99 fast track (SGI-1)Units up to 16 A, total up to 16 A per phaseApply first. Confirmation in 10 days or less instead of 45
G99 fast track (SGI-2)Units up to 16 A, total up to 32 A per phaseExport limiting to 16 A may be required (G100)
G99 fast track (SGI-3)Units up to 32 A, total up to 60 A per phaseExport limiting to 32 A may be required (G100)
G99 standardAnything elseApply and wait for the DNO's connection offer before you switch on

From EREC G98 and G99 Issue 2, with storage requirements in force from 1 March 2026. Export limitation isn't a separate application; it sits inside the G98 or G99 application. Check your DNO's own forms and timescales.

What we do on every job

We check the surveyPhase, main fuse and any existing solar or battery are asked on the survey form. If a job looks like a G99, we flag it before the quote goes out.
G98 includedTap "our team sends it" on Solar job done. We fill it in from the job and send it to the right DNO within 2 working days. How G98 works with us →
Reference chased and filedWe chase the acknowledgement, put the DNO reference on the job and file the proof for your assessor.
G99 from £150Up to 50 kW. We prepare, submit and chase it. Over 50 kW from £200. We never promise approval: that's the DNO's call. G99 application service → · G99 guide →

How we take it off you

Never chase a DNO again.

G98 is included in the £149 a job, and most installers build that into their job price. G99s are an add-on, only when a job needs one.

See pricing

Related

Questions installers ask

What is the G98 limit?

Up to and including 16 A per phase in total at the premises: 3.68 kW on a single-phase supply or 11.04 kW on three phase, for fully type tested equipment.

How long do I have to send a G98?

Within 28 days of commissioning. When our team sends it, it goes within 2 working days of you tapping Solar job done.

Does existing solar count towards the G98 limit?

Yes. The limit is for all generation at the premises, including existing systems and batteries. Adding a battery to an existing 3.68 kW system will usually need a G99.

Is G98 included?

Yes. Preparing, sending and chasing the G98 is part of the £149 per job.

How much is a G99?

From £150 for systems up to 50 kW, and from £200 over 50 kW. We prepare, submit and chase it. Approval is the network operator's decision, so we never promise it.

Sources (checked 21 November 2026)

You survey and fit. We do the rest.

Quote packs, signing, handover packs and G98 on every job, in your name. Under 30 minutes of your time.

Try your first job freeBook a call with us