Installer guide

Adding a battery to existing solar? It's usually a G99.

Battery retrofits are the easy sale. They're also where the DNO paperwork catches people out, because the limit counts everything already on the property.

By Kevin Mallon, founder · Checked 21 November 2026

Why

G98 covers fully type tested micro-generation up to and including 16 A per phase in total at the premises: 3.68 kW single phase, 11.04 kW three phase. Existing solar counts. So a new battery on a home that already has a 3.68 kW system will usually push the site over, and into G99.

The usual way through

  • G99 fast track. For fully type tested solar and storage, SGI-1 to SGI-3 cut the DNO's confirmation from 45 days to 10 or less. SGI-2 and SGI-3 may need export limiting under G100.
  • Export limitation is part of the application, not a separate one, and adding it doesn't automatically make a job fast track.
  • Apply before you fit. Under G99 the system can't be switched on until the DNO says yes.

At survey, ask three things

  1. Single or three phase?
  2. Main fuse rating?
  3. Any existing solar, battery or other generation? Get the size and the year.

How we take it off you

Our survey form asks all three.

If the answers point to a G99, the job is flagged before the quote goes out. G99s from £150 up to 50 kW: prepared, submitted and chased. We never promise approval.

G98 and G99, handled

Related

Questions installers ask

Does a battery count towards the G98 limit?

Yes. The 16 A per phase limit is for all generation at the premises, including storage and existing solar. A battery added to an existing 3.68 kW system will usually need a G99.

Is there a fast track G99 for batteries?

Yes. For fully type tested solar and storage, the SGI-1 to SGI-3 fast track routes cut the DNO's confirmation from 45 days to 10 days or less. Export limiting may be required for SGI-2 and SGI-3.

Sources (checked 21 November 2026)

You survey and fit. We do the rest.

Quote packs, signing, handover packs and G98 on every job, in your name. Under 30 minutes of your time.

Try your first job freeBook a call with us