G98 and G99 with National Grid Electricity Distribution: what installers need to know.

Applying to National Grid Electricity Distribution for a solar or battery job: which route, which form, and what to check first.

By Kevin Mallon, founder · Checked 24 November 2026

Short answer: National Grid Electricity Distribution (formerly Western Power Distribution) has an online form for G99 fast track applications, with instant acknowledgement for eligible jobs. Emailed or posted applications get a response within 10 working days. G98 is notified within 28 days of commissioning.

Who National Grid Electricity Distribution covers

The East Midlands, the West Midlands, the South West and South Wales. Not sure? Check the property's postcode on the network operator's own site before you apply.

How applications go in

JobHow it goes to National Grid Electricity Distribution
G98Notify within 28 days of commissioning, using its G98 connection procedures.
G99 fast track (SGI-1)Notification only, on form A3-3. Every device and the total must be 16 A or less per phase.
G99 fast track (SGI-2 and SGI-3)Apply first on form A1-2, then notify within 28 days of commissioning on form A3-2 (SGI-3). SGI-2 is up to 32 A total, SGI-3 up to 60 A total.
Larger or not type testedA full G99 application.

Every GB network operator also takes low carbon applications through the Energy Networks Association's free Connect Direct platform.

The online fast track form takes about 15 to 20 minutes for the application, and 10 to 15 minutes for the notification afterwards. You'll need the device reference numbers for new and existing kit, and any export limitation device.

Before you apply, check

  • Total generation at the property, existing solar and batteries included
  • Phase and main fuse, confirmed on the survey, not guessed
  • Inverter and battery type test details
  • Any export limitation, and how it's set
  • The MPAN and the customer's details
  • A single line diagram if it's anything but simple

Where jobs get stuck

  • ✕Missing or wrong details send the application back, and the clock stops
  • ✕Existing kit nobody mentioned changes the total
  • ✕Fitting before the answer arrives on a G99 job
  • ✕No one chasing, so the install date slips

How we take it off you

Send us the job. We'll deal with National Grid Electricity Distribution.

We prepare your G99 from the job, submit it, chase it and file every reply, from £150 up to 50 kW. G98 is included on every job with the paperwork service. We never promise approval: that's the network operator's call.

G99 application service

Related

Questions installers ask

How do I apply for G99 with National Grid Electricity Distribution?

Use National Grid Electricity Distribution's own G99 forms or the Energy Networks Association's Connect Direct platform. Small type-tested systems may qualify for the fast track.

How long do I have to send a G98 to National Grid Electricity Distribution?

Within 28 days of commissioning.

Can I fit before G99 approval?

Don't switch on until the network operator has given its answer. Book the install once you have it.

Can you do it for me?

Yes. G99 applications from £150 up to 50 kW, and G98 is included with the paperwork service.

Sources (checked 24 November 2026)

You survey and fit. We do the rest.

Quote packs, signing, handover packs and G98 on every job, in your name. Under 30 minutes of your time.

Try your first job freeBook a call with us