Everything the redeveloped MCS scheme says your customer gets at handover and in the 30 days after, line by line, with the clause beside it.
By Kevin Mallon, founder · Checked 24 November 2026
Short answer: under the MCS Customer Commitment, your customer gets a demonstration of the system and a handover pack at the end of the job, then the MCS certificate and any network operator and Building Regulations paperwork within 30 calendar days. Here is the full list, with where each line comes from.
| Check | Where it comes from |
|---|---|
| Show them how the system works and its key parts | Customer Commitment 5a to 5b |
| Show them how to set it up and use it, and agree how they'll control it | Customer Commitment 5b to 5c |
| Check they're happy with the work, and agree a date for anything still to do | Customer Commitment 5d to 5e |
| Explain what to do and who to contact if something goes wrong | Customer Commitment 5j |
| Generation readings they can see without a tool, ladder or torch | MIS 3002, 3.7.3 |
| A way to tell them within 48 hours if the system stops or runs abnormally | MIS 3002, 3.7.5 |
| Update the network login on any internet-connected kit, with the customer | MIS 3002, 3.7.6 |
The Customer Commitment (5f) sets the minimum. Tick every line on every job:
| Check | Where it comes from |
|---|---|
| A list of the key parts installed | Customer Commitment 5f |
| Health and safety guidance | Customer Commitment 5f |
| A servicing and maintenance schedule | Customer Commitment 5f |
| The manufacturers' manuals | Customer Commitment 5f |
| All guarantees and warranties | Customer Commitment 5f |
| What the guarantees and warranties cover, and the customer's right to refuse any protection offered | Customer Commitment 5g |
| What they must do to keep guarantees and warranties valid | Customer Commitment 5h |
| Whether any ongoing checks or monitoring apply | Customer Commitment 5i |
| The commissioning and test results (MIS 3002 gives a model verification certificate and array test report) | MIS 3002, 4.1 and Appendix C |
| Check | Where it comes from |
|---|---|
| The MCS certificate | Customer Commitment 5k |
| Building Regulations compliance certificate, where needed | Customer Commitment 5k; notify before handover where you're responsible (MIS 3002, 3.1.4) |
| Proof of G98 notification or G99 approval from the network operator, where needed | Customer Commitment 5k; MIS 3002, 3.1.6 |
How we take it off you
Your handover pack, built after every job.Tap Solar job done on your phone and we build the pack in your company name: handover document, warranties, manuals, certificates and an SEG export guide, checked by a second person. Your Technical Supervisor signs it. Included in the £149 a job.
MCS handover pack serviceRelated
At minimum, under the MCS Customer Commitment (5f): a list of key parts, health and safety guidance, a servicing and maintenance schedule, manufacturers' manuals, and all relevant guarantees and warranties.
Within 30 calendar days of the installation being completed, along with any Building Regulations certificate and proof of the network operator notification or approval (Customer Commitment 5k).
Not as a single list. It covers commissioning, test records and a model verification certificate. The handover pack contents come from the Customer Commitment.
At least six years (Customer Commitment 2g).