Home › Installer guides › MCS audit checklist
Installer guide
The evidence to have ready for an MCS assessment under the redeveloped scheme, from every installer to firms with subcontractors, with the source beside each line.
By Kevin Mallon, founder · Checked 24 November 2026
Short answer: on assessment day your assessor wants proof, not promises: in-date qualifications and insurance, a complaints log, six years of secure records, your certificates and building notifications, and a finished installation with a full file and your Technical Supervisor on hand. What else they look for depends on your operating scenario, A to D.
| Check | Where it comes from |
|---|---|
| A named Main Contact for scheme queries | NAPIT checklist, Scenario A |
| In-date Technical Supervisor qualifications, MCS-recognised or ISO/IEC 17024 | NAPIT checklist |
| In-date insurances | NAPIT checklist |
| Access to current MCS documents, MIS 3002, the relevant Approved Documents, the IET Code of Practice and BS 7671 | NAPIT checklist, Scenario A |
| A complaints log, with what you learned and changed | NAPIT checklist; Customer Commitment 6c |
| Installation records kept securely, in line with data protection law, for at least six years | NAPIT checklist; Customer Commitment 2g |
| Building notifications and MCS certificates for the last 12 months (existing installers) | NAPIT checklist, Scenario A |
| Quotes and installations that match your certified scope | NAPIT checklist, Scenario A |
| MCS certificates raised within 30 calendar days of commissioning | Installer Operating Requirements, 4.10 |
| Check | Where it comes from |
|---|---|
| Your responsible Technical Supervisor there throughout | NAPIT checklist, on-site assessment |
| A finished, commissioned installation with the full installation file | NAPIT checklist, on-site assessment |
| Risk assessments done before work started | NAPIT checklist, on-site assessment |
| The G98 notification or G99 application, and how you decided which applied | NAPIT checklist; MIS 3002, 3.1.6 |
| Commissioning and test records | MIS 3002, 4.1 |
| You can answer questions on the standards and Building Regulations | NAPIT checklist, on-site assessment |
Your certification body may ask for more: NAPIT says its own checklist is not exhaustive. Check the Installer Operating Requirements and your certification body's guidance before your date.
How we take it off you
Every job filed, ready for your assessor.On the paperwork service every job gets a numbered, indexed file, certificate deadlines are tracked, and key dates for calibration, Technical Supervisor certificates and insurance are chased. The Records & Audit Pack adds an assessment summary before your assessor visits.
See pricesRelated
Proof that you meet the scheme: in-date qualifications and insurance, a complaints log, secure records kept for at least six years, recent MCS certificates and building notifications, and a completed installation with its full file and your Technical Supervisor present.
A, B, C or D, set by your head count, subcontractors and how many regions you work in. It decides how much your assessor expects to see.
Yes. The responsible Technical Supervisor should be available throughout the on-site assessment.
Certification bodies publish their own guidance. This list draws on NAPIT's checklist, the MCS Customer Commitment, MIS 3002 and the Installer Operating Requirements. Check your own certification body's guidance too.