Home › Installer guides › The MCS certificate 30-day rule
Installer guide
The redeveloped scheme gives you 30 calendar days from commissioning to raise the MCS certificate, up from 14. More breathing room, but your customer is waiting on it.
By Kevin Mallon, founder · Checked 21 November 2026
Clause 4.10 of the MCS Installer Operating Requirements: raise an MCS certificate within 30 calendar days of commissioning an installation.
Commissioning date, MPAN, generation meter make, model, serial and reading, declared net capacity, mounting type, final price and your kit. Get them on the day, not from memory three weeks later.
How we take it off you
Ready to copy, or lodged for you.Solar job done collects everything the certificate needs, on site, on your phone. We put it on one ready-to-copy sheet and chase you before the deadline. Or we lodge it for you for £29.
See add-onsUnder the redeveloped MCS scheme, 30 calendar days from commissioning. It was 14 days under the previous scheme.
They need it to apply for the Smart Export Guarantee, and it's their proof the installation meets MCS standards.
Quote packs, signing, handover packs and G98 on every job, in your name. Under 30 minutes of your time.